Waterfalls 102 – Adding Rules
(Updated 09/27/2018)

You will now be prompted to add your first rule that is applicable to this Waterfall.  Name your rule, and if desired add your Operating Agreement Section description.  Then select the template, that best describes the calculation you need to perform.  You will find a detailed description of each of the rule templates and how specific fields impact calculations here.

102_1.png 

Once you select your rule template, the appropriate inputs will be revealed.  Specific functionality around each of the templates and their associated inputs can be found here.  Input your values for the template and save.

102_2.png

Your rule will be saved and you will see a summary of your first rule in a narrative format.  You can Open the rule to edit your parameters, edit the name of the rule, or delete the rule all together.  To add your next rule in the waterfall, select “Add New Rule”.

102_3.png

You will be prompted to name a new rule and select the appropriate template.  In this example, we will select the Return of Capital template.

102_4.png

Select the appropriate inputs and save your rule.

102_5.png

Now you will see your two rules in the order they will run when distributing funds through the waterfall.

102_6.png

Continue adding rules to your waterfall until you have all of your waterfall scenarios built to distribute cash flow.  In the event you add the rules in the incorrect order, you can drag and drop the rules with your mouse without deleting and re-inputting.

As discussed earlier, you can have multiple waterfalls for an Entity.  If you need to add additional, you can select the “Back to All Waterfalls” to create another.

102_7.png

You will find a list of all Waterfall rulesets for the Entity on this page and can select “Add Waterfall” if you need to create another.

102_8.png

Once you are done adding Waterfall rulesets for a given Entity, you can move to the next Entity.  You can navigate to the Waterfall tab for the next Entity you want to work on by selecting the Entity Name drop down.  You can always exit and return via the Project Summary or Home tab to continue editing and adding Waterfall rulesets.

If your Project is a single tier structure, then you are done and can begin running distribution calculations.  To see instructions on how to run and manage distributions, click here.  We will now continue with building a Project Level Waterfall which allows you to run a series of rulesets across entities in one setup.